Demolition has begun!!

View our progress below.

Week #1 - October 1-7, 2007 - rectory building demolished

Week #2 - October 8-14, 2007 - trees removed from site

Week #3 - October 15-21, 2007 - awaiting building permit, no activity on site

Week #4 October 22-28, 2007 - Rain delay!

Week #5 October 29- November 4, 2007 - site grading done

Week #6 - November 5-11, 2007 - deep foundation work begun

Week #7, 8, 9 - foundation work continues with several rain delays

Week #10 & #11 - December 3-14, 2007 - beginnings of ground foundations

Week #12 & #13 - December 15-29, 2007 - new sewer line is run

Week #14 & #15  - Dec 30, 2007 - Jan 12, 2008 - work on sewer line and ground foundations continue

Week # 16 & #17 - January 13-26, 2008 - foundation work continues

Week #18 & # 19 - January 27-February 9, 2008 - foundation nearly complete - backfilling begun

Weeks #20-#24 Feb 10-March 7, 2008 - backfilling continues

Weeks #25-#28 - March 8-April 4, 2008 - backfilling complete - Steel goes up!

Weeks #29 & #30 - April 5-18, 2008 - Roof goes on - block walls begin

May 2008 - Block walls continue to rise, plumbing rough-in for kitchen and bathrooms begun, concrete floor poured

June 2008 -  Block veneer begins and steel work continues to roof and upper building