|
|
||
|
|
"Reflecting God's love for over 150 years |
|
|
Parish Multi-purpose Facility planned for St. Agnes Demolition has begun!! View our progress below. Week #1 - October 1-7, 2007 - rectory building demolished Week #2 - October 8-14, 2007 - trees removed from site Week #3 - October 15-21, 2007 - awaiting building permit, no activity on site Week #4 October 22-28, 2007 - Rain delay! Week #5 October 29- November 4, 2007 - site grading done Week #6 - November 5-11, 2007 - deep foundation work begun Week #7, 8, 9 - foundation work continues with several rain delays Week #10 & #11 - December 3-14, 2007 - beginnings of ground foundations Week #12 & #13 - December 15-29, 2007 - new sewer line is run Week #14 & #15 - Dec 30, 2007 - Jan 12, 2008 - work on sewer line and ground foundations continue Week # 16 & #17 - January 13-26, 2008 - foundation work continues Week #18 & # 19 - January 27-February 9, 2008 - foundation nearly complete - backfilling begun Weeks #20-#24 Feb 10-March 7, 2008 - backfilling continues Weeks #25-#28 - March 8-April 4, 2008 - backfilling complete - Steel goes up! Weeks #29 & #30 - April 5-18, 2008 - Roof goes on - block walls begin May 2008 - Block walls continue to rise, plumbing rough-in for kitchen and bathrooms begun, concrete floor poured June 2008 - Block veneer begins and steel work continues to roof and upper building |
||